[Next] [Previous] [Top]

ECE241F Lab Information

Lab and Project Schedule

Monday

of Week

Lab

 

Sept 21

Lab1 - Introduction to Combinational Logic and TTL

postscript

Sept 28

Lab 2 - Altera Software Intro and Tutorial

postscript

Oct 5

Lab 3 - 7-Segment Combinational Logic Design

postscript

Oct 12

Week of MIDTERM, no lab

 

Oct 19

Lab 4 - Sequential Logic and Hierarchical Design

postscript

Oct 26

Lab 5 - Adders and Registers

postscript

Nov 2

Lab 6 - Finite State Machines

postscript

Nov 9

Lab 7 - Complex Finite State Machine Modules and Handshaking Project Proposal Due this week, in lab day.

postscript

Nov 16

Project Week 1

 

Nov 23

Project Week 2

 

Nov 30

Project Week 3; additional lab periods in evening will be available.

 

 

Project Report Due December 4